Home > Resources > Case Studies > Article
At Collegiate School in New York City, construction photo documentation became a long-term visual record that helped the facilities team investigate building conditions, resolve warranty questions, locate concealed systems, and support facilities operations. The school ultimately attributed $3.7 million in post-construction savings to two issues documented in that record.
During construction of the school’s nine-story, 175,000-square-foot campus, documentation specialists from Hexagon Multivista, part of Hexagon, captured more than 14,900 photos. The facilities team later added more than 280 images of its own.
When problems emerged after occupancy, that extensive visual record gave the team a way to investigate what had been installed without opening finished walls.
| Customer | Collegiate School |
| Location | New York City |
| Facility | 9-story, 175,000-square-foot school |
| Service | Construction photo documentation |
| Visual record | More than 14,900 professionally captured photos; more than 280 images added by the school. |
| Reported post-construction savings | $3.7 million |
| Primary uses | Quality verification, warranty investigation, concealed-system location, and facilities reference |
While the new building was under construction, Collegiate School remained open for students. The facilities team could not be present on the jobsite every day, so construction photography provided another way to follow progress.
Construction photo documentation gave the Collegiate School facilities team another way to follow progress while the new building was under construction. Because the team could not be present on the jobsite every day, the visual record helped maintain visibility into work taking place in the field. Collegiate School described construction-phase savings of hundreds of thousands of dollars.
Maintaining that visual record also preserved information that would later prove useful after handover.
Two years after classes began in the new building, the facilities team noticed unusually cold conditions in one area during the winter. A building-wide energy evaluation also indicated poor performance.
Once construction is complete, many of the components that influence building performance are no longer visible. Insulation, piping, electrical conduit, structural support, and other systems may sit behind finished walls and ceilings. Investigating those conditions can require teams to rely on project records or physically open finished surfaces.
However, Collegiate School was able to use the Hexagon Multivista photo documentation and could return to the visual record to review conditions captured before the walls were closed.
Progression photos showed the walls at multiple stages of construction, helping the facilities team identify where insulation was missing without opening every wall. The visual record captured conditions from open framing through the installation of piping, electrical systems, insulation, and drywall.
Mark Gordon, Director of Facilities at Collegiate School, explained that without the visual record, the team would otherwise have needed to “cut into every wall” to confirm where insulation was missing. Instead, he was able to use the construction photos to narrow down potential targets before opening finished surfaces.
Collegiate School attributed $1.7 million in savings to identifying and addressing the insulation issue using the construction record.
The example demonstrates one of the long-term uses of Hexagon Multivista Capture services: information collected while work is still visible is highly useful when teams need to understand concealed conditions later in the asset lifecycle.
When outdoor play surfaces began separating from the foundation, date-stamped photos helped the facilities team establish when the flooring had been installed. The team then cross-referenced the installation date with city weather information.
They determined that installation had taken place when the temperature was 17°F, while the product instructions referenced by the school required 40°F. With the installation date and conditions documented, Gordon summarized the investigation simply: “That was an easy one.”
Collegiate School attributed $2 million in savings to resolving the flooring issue.
Together, the insulation and flooring cases account for the $3.7 million in customer-reported post-construction savings highlighted in this case study.
The visual record also helped the Collegiate School facilities team locate systems concealed behind finished surfaces. As maintenance, repairs, and upgrades arose, the team could return to construction documentation to better understand what was behind the walls. Gordon said “we use Hexagon Multivista photo documentation all the time” to look back at conditions behind the walls.
For facilities teams, that type of historical visual context can help narrow an investigation before physical work begins. Instead of starting without visibility into what may be behind a finished surface, teams can first review what was documented during construction.
That long-term value is particularly relevant for education facilities, where buildings must support ongoing operations while maintenance, renovation, and future capital work continue over time.
The value of the Collegiate School documentation extended across both construction and operations.
The outcome was not based on collecting more project information for its own sake. The value came from having relevant information available when a specific question needed to be answered.
A similar principle appears in the Swinerton construction photography case study, where visual records of concealed conditions also helped a project team avoid destructive verification.
Construction photo documentation can remain valuable after handover because it preserves visual context that may be difficult or impossible to recreate once assemblies are covered, and finishes are installed.
A structured visual record can preserve context from those earlier stages. When documentation is organized by location and date, teams can return to captured conditions as questions arise during warranty periods, maintenance, renovation, or facility operations.
The Collegiate School experience shows how that continuity can turn construction photography into more than a progress record. The same images used during construction later helped the facilities team investigate defects, review installation conditions, locate concealed systems, and make decisions with more information about what had actually been built.
Construction photo documentation can help preserve visibility into conditions that will eventually be concealed, giving project and facilities teams a record they can return to throughout the building lifecycle.
Ready to discuss how photo documentation could support construction oversight, handover, and long-term facility needs? Book a 30-minute consultation.
We can walk you through a tailored plan based on your workflow, stakeholders, and project phase.